Nepal stranded contracts review: six sick contracts face termination, six projects completed

Nepal stranded contracts review: the ministry continued its detailed review on Wednesday of projects and programmes run by the Local Infrastructure Development Department under the Ministry of Infrastructure Development. Infrastructure Development Minister Sunil Lamsal said the ministry is studying and reviewing contracts that are stranded or sick in close detail, rather than leaving them to drift. The review, reported on November 4, 2026, is part of a sustained effort to separate projects that can still be completed from contracts that should be ended and restarted.

The department had 19 sick contracts under review. Of those, the minister said a decision has been taken to move ahead with terminating six contracts where there is no prospect of progress. Terminating a contract is a serious step, since it requires a fresh process to bring in a new contractor, but the ministry’s position is that keeping a non-performing contract in place can cost more time than starting again with a workable plan and a realistic schedule. A clear decision, even when difficult, can free a project from a long period of uncertainty and allow planning to begin again on a firmer footing.

At the same time, the review reported progress on other fronts. After continuous monitoring and facilitation by the ministry, six projects have been completed, and construction work on five more projects has moved forward. That mixed picture is important, because it shows the review is not only about ending contracts. It is also about identifying which projects can be pushed to completion with closer supervision, clearer instructions, and support to remove bottlenecks. Completion of six projects gives communities usable facilities or routes, while progress on five more suggests that targeted help can change the course of a project that was at risk of stalling.

Monitoring and facilitation can take many practical forms. They may include regular site checks, quicker decisions on technical or administrative questions, coordination between offices, and follow up when a contractor reports a problem. When those steps are taken consistently, small delays are less likely to grow into long stoppages. When they are missing, even a project with a sound design can drift, as each unresolved issue adds to the next. The ministry’s emphasis on continuous monitoring therefore points to a change in day to day management, not only in high level decisions about termination.

Nepal stranded contracts review: revised action plan and next steps

As part of the Nepal stranded contracts review, the minister said the action plan for local infrastructure construction has been revised, and instructions have been given to speed up the implementation of projects and programmes. A revised action plan can help only if it changes what happens on site, so the next test will be whether the six terminations proceed promptly, whether the five advancing projects keep their momentum, and whether completed projects are handed over in usable condition. Speed must be matched by quality, because a project finished in haste but not fit for use will create new problems for the community it was meant to serve.

Local infrastructure projects often matter most at the ward and municipality level, where a single road, drainage, or public building project can affect daily access to markets, schools, and health services. When such projects stall, the cost is not only financial. Communities plan around a promised facility or route, and a long delay can undermine trust in the delivery system itself. Regular review, public reporting of decisions, and follow through on retendering are therefore central to whether this drive restores confidence. People need to see not only announcements, but also workers, materials, and completed works.

The Nepal stranded contracts review should also be read alongside the ministry’s wider termination drive, including the termination of stranded contracts across Nepal and the termination of three stranded contracts in Banke and Bardiya. Together, these decisions point to a ministry wide approach: end contracts with no prospect of progress, support projects that can advance, and revise plans where implementation has slowed. If that approach is applied consistently, with clear timelines and public updates, it could reduce the number of sick contracts over time and improve delivery for local communities across Nepal.

Source: Minister Sunil Lamsal’s Facebook post, November 4, 2026: https://www.facebook.com/ersunillamsal/posts/pfbid026hF1bB1GkYCWXMFWVAx6YDdEhp6MC95dSVAZqquVJpRUArGY6QXLnaqSwAitGdTHl