The Hudson Tunnel Project has started excavation of its second rail tube in New Jersey, putting both tubes of the 16 billion dollar rail megaproject under construction at the same time. The Gateway Development Commission said on November 18, 2026 that a second tunnel boring machine has begun digging the southern tube, following the start of the northern tube machine in October. The announcement means the most urgent passenger rail project in the United States, in the words of the commission, now has two giant machines working underground at once.
The first machine has already advanced about 400 feet and installed more than 60 precast concrete lining rings, according to the commission. The second machine began mining on November 18, so the two tubes are now advancing side by side through the rock of the Palisades in northern New Jersey.
Hudson Tunnel Project: what the second machine will dig
The two machines are excavating parallel 5,100 foot sections through the Palisades, running from the tunnel portal in North Bergen to the Hudson County Access Shaft near the Weehawken and Hoboken border. The commission expects this first stretch of tunnelling to take about one year, including scheduled maintenance stops.
Each machine is a single shield tunnel boring machine built to cut hard rock. According to Engineering News-Record, the machines have cutterheads 28 feet 8 inches across, with trailing gantries extending about 500 feet behind the cutting face. As excavation advances, each machine will install nearly 850 tunnel lining rings assembled from more than 5,000 precast concrete segments. The Palisades section also includes six cross passages connecting the two tubes, which will let passengers move between tubes in an emergency and give maintenance crews access along the route.
The Palisades Tunnel construction package is being built by the Schiavone Lane Dragados joint venture, with the Port Authority of New York and New Jersey managing delivery in partnership with the Gateway Development Commission.
Why the Hudson Tunnel Project matters
The Hudson Tunnel Project will provide a new two track passenger rail connection between New Jersey and Manhattan. Its twin tubes will supplement the existing North River Tunnel, which opened in 1910 and is now slated for a full rehabilitation under the Gateway Program. That rehabilitation can only happen in full once the new tunnel is carrying trains, because the old tunnel is the only rail link under the Hudson River for Amtrak and New Jersey Transit trains today.
The project has already survived a serious funding scare. Federal disbursements were suspended in October 2025, work paused at several sites in February 2026, and construction resumed only after the withheld federal payments were released, according to Construction Review Online. The start of the second machine is therefore more than a routine step. It is a public sign that the 16 billion dollar project, which is divided into ten construction packages, is moving again at full pace after that disruption.
The scale of the work is also a measure of how much is at stake. The Northeast Corridor between Washington and Boston is the busiest passenger rail line in the United States, and the Hudson River crossing is its tightest bottleneck. Every delay on this crossing ripples through commuter and intercity services across the region. Two machines digging at once doubles the rate at which the new tubes take shape, and it keeps the project on course for the river crossing that follows.
What happens next for the Hudson Tunnel Project
Once the two machines reach the Hudson County Access Shaft, crews will remove them and deploy a second pair of machines designed for the mixed ground conditions beneath the Hudson River. That river section will advance the tunnelling toward Manhattan, and it is being delivered by the Traylor, Walsh and Skanska joint venture under a separate construction contract awarded in April 2026.
Ground preparation for the river crossing is already under way. The commission reported in its fall 2026 construction update that about 1,000 feet of riverbed, more than 100 feet wide, had already undergone stabilization work. The Hudson River Tunnel Section also includes nine cross passages connecting the two new tubes, along with work to stabilize ground near Hudson-Bergen Light Rail tracks and reinforce the foundations of the Willow Avenue Bridge between Weehawken and Hoboken.
The new tunnel is targeted to enter service in 2035, according to Construction Review Online, with rehabilitation of the existing North River Tunnel expected to finish in 2038. Between now and then, the two machines now digging through the Palisades will set the pace for the whole project. If they hold their schedule through the rock, the river crossing can begin on time, and the busiest rail bottleneck in America will finally get the second crossing engineers have been planning for decades.
Source: Engineering News-Record, Gateway Hudson Tunnel Project Starts Excavation of Second Rail Tube, November 18, 2026, https://www.enr.com/articles/64365-gateway-hudson-tunnel-project-starts-excavation-of-second-rail-tube