Troubled Projects Department Nepal: 72 Sick Projects to Leave Department Oversight

The troubled projects department Nepal update was announced on Tuesday, November 3, 2026, Nepal time, after Infrastructure Development Minister Sunil Lamsal reviewed the state of troubled projects under the Department of Urban Development and Building Construction. The minister said the review looked in detail at programmes that have run into serious difficulty, and the meeting reached a clear decision on how those cases should be handled from now on.

According to the figures shared in the announcement, the department oversees 2,807 programmes in total. Of that total, 72 were identified as troubled. The label is used for projects that are not progressing as planned. In public construction, that can mean work has stalled, a deadline has passed without completion, a contract has become difficult to carry forward, or the original plan can no longer be delivered in a practical way. Such projects often remain on official lists for a long time, even when little or no work is taking place on site.

What the troubled projects department Nepal review found

The breakdown of the 72 troubled projects shows a mixed picture, rather than a single problem affecting every case. Ten projects are listed as completed. Four had their contracts terminated. Eight are in the final stage of contract termination. 32 are operating after deadline extensions. 18 have expired deadlines. Together, those five groups account for all 72 projects identified in the review.

The figures matter because they separate projects that can still move forward from those that cannot. A project operating after an extension is not in the same position as a project whose deadline has expired with no clear path to completion. Likewise, a completed project does not need the same action as a contract that is already in the final stage of termination. By sorting the cases in this way, the department can apply a different response to each group, instead of treating every troubled project as if it faced the same difficulty.

Why removing troubled projects from department oversight matters

The meeting decided that contracts for projects where construction is not possible will be terminated, and that troubled projects will be removed from under the department’s oversight. Removing a project from that oversight does not mean the problems behind it disappear. It does mean the project will no longer remain indefinitely on the department’s active list while it waits for a decision. For officials, that can reduce the backlog of unresolved cases and make it easier to see which works are genuinely active. For the public, it can make the status of a project clearer, because a stalled case is formally closed or moved to a new process, rather than left in an uncertain state.

For the troubled projects department Nepal portfolio, the decision also fits a wider effort to deal with stalled and stranded contracts. When a contract cannot be completed as originally agreed, keeping it open can block new work, tie up administrative attention, and delay any attempt to restart the project on a fresh basis. Termination, where construction is not possible, creates a formal end point. That end point can then allow the relevant work to be reconsidered, replanned, or restarted through a new process, where that is appropriate. The announcement does not provide further details of any new process for these 72 cases, and this article does not add any such detail.

What happens next for the troubled projects

Under the troubled projects department Nepal approach described in the announcement, the next step depends on the category of each project. Contracts for projects where construction is not possible are to be terminated. Projects already in the final stage of termination will continue through that process. Projects operating after deadline extensions will continue under those extensions, subject to the terms already agreed for them. Projects with expired deadlines will need a decision on whether they can be brought back into a workable timetable or whether they should also move toward termination.

The announcement, made after the detailed review meeting on November 3, 2026, therefore marks a point of separation. Completed projects can be recorded as complete. Terminated contracts can be closed. Projects that are still operating can be monitored against their extended deadlines. The remaining question is how quickly the decisions on the expired and unfeasible cases are carried out, and whether restarted works, where they are possible, are taken forward through a clear and transparent process. Those steps will determine whether the review leads to visible progress on the ground, rather than only a change in how the projects are listed.

Source: Minister Sunil Lamsal’s Facebook post, November 3, 2026

Related reading: Nepal stranded contracts terminated and Rautahat stranded projects contracts terminated.

Get construction news in your inbox

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top