Iraq Opens Khor Al-Zubair Immersed Tunnel, the Middle East First Submerged Road Tunnel

Dimly lit tunnel interior with lights, similar to the Khor Al-Zubair tunnel in Basra, Iraq
Photo: Pexels

Iraq has opened the Khor Al-Zubair tunnel, a 2.5 kilometre immersed road tunnel beneath the Khor Al-Zubair waterway in Basra, and it is the first immersed tunnel ever built in the Middle East. Transport Minister Wahab Al-Hassani opened the tunnel on Thursday, November 12, 2026, and South Korea’s Daewoo Engineering and Construction formally handed the completed structure over to the General Company for Ports of Iraq, according to Shafaq News.

The opening completes a major component of the Grand Faw Port project and creates a direct road link between the Faw Peninsula and Umm Qasr, Iraq’s main deep-water port. According to the Ministry of Transport, the tunnel will shorten travel distances and reduce the time and cost of moving goods between the two areas.

How the Khor Al-Zubair tunnel was built

An immersed tunnel is built very differently from a bored tunnel. Instead of digging through rock, engineers cast huge concrete sections in a dry basin, float them out to the channel, sink them into a prepared trench on the seabed, and join them together underwater.

The Khor Al-Zubair tunnel is made of 10 concrete sections, each about 125 metres long and weighing around 46,000 tonnes. The tunnel carries six lanes of traffic plus a dedicated emergency lane. According to Ballast Nedam, the Dutch company that carried out the immersion work as a subcontractor to Daewoo, the sections were sealed to each other with Trelleborg Gina gaskets and Omega seals, the flexible joints that keep water out of the tunnel while allowing the sections to move slightly with ground settlement and temperature change.

The ground conditions made the work harder. The tunnel crosses spongy, soft soils on the Basra coast, so geotechnical stability and waterproofing were among the biggest engineering risks. According to Worldsensing, which supplied the monitoring system, engineers tracked groundwater levels around the casting basin with more than 70 analogue data loggers, 40 vibrating wire loggers and 10 digital data loggers, taking readings every five minutes so that any water level rise, for example after heavy rain, could be acted on before it disrupted the works. The project was supervised by the Italian consultancy Technital.

Progress was steady once immersion began. The General Company for Ports of Iraq confirmed the first section was immersed in March 2025, and a fifth section, known as Azal, was later set on the channel bed. By May 9, 2026, construction was more than 95 percent complete, and last month the company’s director general said overall completion had reached 98 percent. The tunnel was delivered under Daewoo’s 2.6 billion dollar engineering, procurement and construction contract for the Grand Faw Port, awarded in December 2020.

Why the Khor Al-Zubair tunnel matters

The tunnel is small in length but large in consequence. It is the missing road link in the Grand Faw Port, a project Iraq expects to become one of the 20 largest container terminals in the world, handling nearly 99 million tonnes a year. Daewoo has also built the port’s breakwater, described as the longest in the world, and completed a 62 kilometre connection road between the new port and Umm Qasr in July 2026.

Beyond the port, the tunnel plugs into Iraq’s 17 billion dollar Development Road project, a roughly 1,200 kilometre road and rail corridor planned to carry goods from the Gulf to Turkiye and on to Europe. The idea is to offer an overland alternative to the Suez Canal route for Asia to Europe freight, with containers unloaded at Faw and moved north by road and rail. Whether that ambition is realised will depend on the railway, the port operator and regional politics, but the tunnel removes one physical bottleneck from the southern end of the corridor.

The project also matters as a first. No immersed tunnel had been built in the Middle East before this one, and the method, casting sections on land, floating them into place and joining them underwater, is now proven in the Gulf’s soft soils and tidal conditions. That experience is directly transferable to other coastal crossings in the region.

What happens next

With the tunnel open, attention turns to the rest of the Grand Faw Port. The General Company for Ports of Iraq has begun the handover process for five berths, which it says have reached 100 percent completion, while the port road is about 92 percent complete. The company expects the port, including all related projects, to be completed and operational next year.

For engineers, the next test is operation: how the immersed sections settle, how the seals perform under traffic and tidal loading, and how the ventilation and safety systems cope with real vehicles. If the tunnel performs as designed, Iraq will have proved that one of the most demanding tunnelling methods can be delivered on its southern coast, and the Development Road corridor will have its first fully working link.

Source: Shafaq News, November 12, 2026 (https://en.hathalyoum.net/articles/306297)