Kankai Bridge Completed Ahead of Schedule, Opens to Traffic in Jhapa

The Kankai bridge completed ahead of schedule is now carrying traffic in eastern Nepal, after construction finished months before the contract deadline. Infrastructure Development Minister Er. Sunil Lamsal announced on Sunday, November 15, that the bridge over the Kankai River has been fully opened for public use.

The bridge connects Shivasatakshi Municipality and Jhapa Rural Municipality in Jhapa district, two local areas on opposite banks of the Kankai River. For residents, the crossing removes a long standing barrier to daily travel, trade and access to markets, schools and health services on either side of the river.

Kankai bridge completed ahead of schedule

Work on the bridge began under a contract signed on 2079 Poush 11, in late December 2022, with completion scheduled for 2083 Ashoj 10, in late September 2026. The construction team finished the work before that date, and the bridge is now in full operation.

Minister Lamsal presented the early finish as more than a single project milestone. In his announcement he said the bridge shows the pace the government wants for infrastructure work, and that he wants every infrastructure project in the country to finish ahead of its scheduled time.

Why the Kankai bridge matters for Jhapa

Jhapa is one of the busiest districts in eastern Nepal, and the Kankai River has long divided communities that trade and travel across it every day. A reliable bridge shortens journeys, cuts transport costs for farmers and traders, and gives emergency vehicles a direct route that did not exist before. During the monsoon, river crossings in the Tarai often become risky or impossible, so a permanent bridge also adds safety in the months when water levels rise.

The early completion also matters for the ministry’s wider programme. In recent weeks the minister has reported a series of bridge and road completions across the country, including Bailey bridges in Rasuwa and approach work on the Maldhunga bridge. Finishing the Kankai bridge before its deadline adds to that record and sets a benchmark the ministry can point to when it presses contractors on other delayed projects.

What happens next

With the bridge open, the focus now shifts to keeping the crossing in good condition and to the approach roads on both banks, which carry the traffic the bridge now serves. The bridge is in full operation as of the minister’s announcement, and no further construction work on this crossing has been announced.

Related reading: Mechi Highway Ilam Upgrade Gains Speed on Flood-Hit Stretch and Maldhunga Bridge Reconstruction.

Source: Minister Sunil Lamsal’s Facebook post, November 15, 2026.