Legal Checklist: Do These Before You Sign
Building your dream home is likely the biggest investment of your life. In Nepal, most house construction disputes have one root cause: there was no proper written agreement, or the agreement was vague. Complete this checklist before you sign anything with a contractor.
1. Confirm the land is legally yours
Check your Lal Purja (land ownership certificate). Visit the Malpot (Land Revenue Office) and confirm the land is registered in your name, with no hidden bank mortgage, no mohi (tenant) claim, no ongoing court case, and land use that allows residential construction. Never build on disputed land.
2. Get your Naksa Pass (building permit) first
Under the Building Act 2055 and Building Rules 2066, your drawings must be approved by the municipality or rural municipality before construction starts. You will need your Lal Purja copy, trace naksa and blue print from the Napi office, citizenship copy, land tax receipt, ward recommendation, and architectural plus structural drawings from a registered engineer or consultancy. Construction is approved in stages: a temporary permit up to plinth level, the superstructure permit after plinth inspection, and finally a completion certificate. Building without a permit, or beyond the approved drawings, can bring demolition orders and blocks your electricity and water connections, bank loans and future sale.
3. Verify the contractor
Ask for the company or firm registration certificate, PAN (and VAT where applicable), and recent tax clearance. Then do the step most people skip: visit at least one house the contractor has completed and ask that owner about quality, delays and how extra work was handled. A contractor who cannot show registration documents or past work is a red flag.
4. Put everything in writing
Nepal’s National Civil Code 2074 allows contracts in written, verbal or conduct form, but a verbal deal is extremely hard to prove in a dispute. A written, signed agreement with clear scope, price, timeline and payment terms is your only real protection. Never start work on a handshake.
5. Read every clause, and get a lawyer for big contracts
Understand the payment schedule, delay penalties, defect liability and termination clauses before you sign. For high value contracts, have a lawyer review the draft. It costs little compared to the house. Never sign blank pages, undated documents, or an agreement you have not read fully.
6. Attach identity and registration documents
Attach citizenship copies of both parties to the agreement. If the contractor is a company, attach its registration certificate and PAN copy, and confirm the signatory has written authority to sign for the company. Both parties should sign in the presence of at least two witnesses, who also sign with their citizenship numbers.
7. Affix revenue stamps and keep originals
Affix revenue stamps on the agreement as per prevailing practice, and prepare at least two originals so each party keeps one signed copy. Store yours safely. It is your evidence if things go wrong.
8. Structure payments around milestones, not promises
Avoid large advances. A mobilization advance of up to 10 to 15 percent is common practice. Link every further payment to verified, measured work or clear milestones: foundation, plinth, each slab, roofing, finishing. Hold back 5 to 10 percent as retention money until the defect liability period ends. Pay by bank transfer or cheque and keep every receipt.
9. Fix responsibility for safety and insurance
The contractor must provide site safety, scaffolding and first aid, and comply with Nepal’s labour laws on wages and working hours. Workers should be insured against accidents. For larger projects, ask for a Contractor’s All Risk insurance policy. Write down who is responsible if a worker or a neighbour is harmed due to site negligence.
10. Agree on dispute resolution in advance
Decide before signing how disputes will be settled: negotiation first, then mediation or arbitration, or the competent court. Write it into the agreement. Settling this while relations are good saves enormous pain later.
11. Plan for handover and the completion certificate
Define handover in the agreement: joint inspection, a snag list, and written handover. After construction, obtain the completion certificate from the municipality. You will need it for utility connections, loans and resale.
Disclaimer: This is general guidance and a sample format, not legal advice. Laws and municipal practices change, so consult a lawyer before signing, especially for high value contracts.
House Construction Agreement Format (Nepal)
Copy the format below or download it as a Word document. Fill in the blanks, delete the options that do not apply, attach the listed documents, and sign with witnesses.
<
Prefer not to fill it by hand? Use our online form and get the completed agreement by email.
a href=”https://eve-construction.com/wp-content/uploads/2026/10/house-construction-agreement-nepal.docx” style=”display: inline-block; background-color: #1B2A4A; color: #ffffff; font-weight: bold; padding: 14px 28px; border-radius: 8px; text-decoration: none;”>⬇ Download House Construction Agreement (Word .docx)
HOUSE CONSTRUCTION AGREEMENT (Ghar Nirman Samjhauta)
This Agreement is made on this ______ day of ____________, 20____ (B.S. ____________) at ____________, Nepal.
BETWEEN
Mr./Mrs./Ms. ________________________, son/daughter/wife of ________________________, permanent resident of ________________________, holding Nepali Citizenship Certificate No. ______________, issued from ______________, (hereinafter called the “Owner” or “First Party”),
AND
________________________ [Contractor name / Company name], having its office at ________________________, registered under ________________________ with Registration No. ______________, PAN No. ______________, represented by Mr./Mrs./Ms. ________________________, (hereinafter called the “Contractor” or “Second Party”).
The Owner and the Contractor shall individually be called a “Party” and collectively the “Parties”.
WHEREAS the Owner is the lawful owner of the land situated at ________________________ (District: __________, Municipality/Rural Municipality: __________, Ward No. ____, Kita (Plot) No. ____, Area: ________), held under Land Ownership Certificate (Lal Purja) No. __________;
AND WHEREAS the Owner has obtained building permit (Naksa Pass) No. __________ dated __________ from ________________________ Municipality/Rural Municipality for construction of a residential house as per the approved drawings;
AND WHEREAS the Contractor has agreed to construct the said house for the Owner on the terms and conditions set out below;
NOW THEREFORE the Parties agree as follows:
1. SCOPE OF WORK. The Contractor shall construct a ______-storeyed residential house on the above land, strictly as per the approved architectural, structural, sanitary and electrical drawings and the Bill of Quantities (BOQ), attached as Annex 1 and Annex 2, which form part of this Agreement. All work shall comply with the Nepal Building Code (NBC) and the conditions of the building permit.
2. CONTRACT PRICE (choose 2A or 2B and delete the other). 2A. Lump sum: The total lump sum price is NPR ____________ (in words: Nepalese Rupees ________________________________ only). This firm price covers all labour, materials (as per Clause 5), tools, equipment and supervision needed to complete the house ready for occupation. 2B. Item rate: Work shall be measured and paid as per the item rates in the attached BOQ (Annex 2). The estimated contract value is NPR ____________ (in words: Nepalese Rupees ________________________________ only). Payment shall be made only for work actually executed and jointly measured.
3. PAYMENT SCHEDULE. 3.1 Mobilization advance: NPR ____________ (not exceeding 15% of the contract price), payable within ____ days of signing. The advance shall be adjusted proportionally from running bills. 3.2 Running bills: The Contractor shall submit running bills every ______ (week/fortnight/month). The Owner or the Owner’s engineer shall verify measurements within ____ days and release ____% of the certified amount within ____ days. 3.3 Retention money: ____% (commonly 5 to 10%) shall be retained from each bill and released after the defect liability period, after deducting the cost of any unrectified defects. 3.4 Final bill: payable within ____ days of handover and joint final measurement. 3.5 All payments shall be made by bank transfer or cheque. Cash payments, if any, must have signed receipts.
4. TIME FOR COMPLETION. 4.1 Work shall commence within ____ days of signing and be completed within ______ months/days, i.e. by ____________ (date). 4.2 For delay, liquidated damages of NPR ____________ per day shall apply, up to ____% of the contract price. (Delete if not agreed.) 4.3 Extension of time is allowed only for causes beyond the Contractor’s control (natural calamity, Owner-caused delay, major approved variation), applied for in writing within ____ days of the event.
5. MATERIALS. 5.1 (Choose one: a) All materials shall be supplied by the Contractor as per Annex 3 specifications. / b) The Owner shall supply: ____________. All other materials shall be supplied by the Contractor.) 5.2 Cement, steel, aggregates and major materials shall be of the brands and grades in Annex 3. No substitution without the Owner’s prior written approval. 5.3 The Owner or the Owner’s engineer may inspect and reject non-conforming materials.
6. CONTRACTOR’S OBLIGATIONS. Deploy adequate skilled manpower, tools and supervision; ensure site safety, scaffolding and first aid; comply with Nepal’s labour laws on wages, working hours and compensation; insure workers against accidents (Contractor’s All Risk insurance if agreed: Yes / No); keep the site clean and protect neighbouring property; allow the Owner and the Owner’s engineer free access for inspection at all times.
7. OWNER’S OBLIGATIONS. Hand over the site on the start date; make payments per Clause 3; provide approved drawings and timely decisions on variations (within ____ days); arrange site electricity and water (or as agreed: ____________).
8. VARIATIONS AND EXTRA WORK. No extra or varied work shall be executed without the Owner’s prior written approval, with rates recorded in writing before execution. Rates follow the BOQ where applicable, otherwise mutually agreed market rates.
9. QUALITY, TESTING AND SUPERVISION. Workmanship and materials shall meet the specifications and NBC standards. The Contractor shall carry out material tests (e.g. concrete cube tests) as specified and share reports. The Owner may appoint an engineer for stage-wise supervision.
10. DEFECT LIABILITY PERIOD. ____ months (commonly 12 months) from handover. The Contractor shall rectify, free of cost, all defects in materials or workmanship appearing in this period, within ____ days of written notice.
11. HANDOVER. On completion, the Parties shall jointly inspect the works, prepare a snag list, and record handover in writing after snags are cleared. The Contractor shall hand over keys, warranties, test reports and as-built drawings (if agreed).
12. TERMINATION. Either Party may terminate with ____ days’ written notice if the other materially breaches and fails to remedy within ____ days of notice. On termination, executed work shall be jointly measured and paid for, less advances and recoveries.
13. FORCE MAJEURE. Neither Party is liable for failure due to earthquake, flood, war, epidemic, government restriction or other events beyond reasonable control, with prompt written notice.
14. DISPUTE RESOLUTION. Disputes shall first be settled by mutual negotiation within ____ days, failing which by mediation/arbitration in ____________, or by the competent court of Nepal. (Choose one and delete the other.)
15. GOVERNING LAW. This Agreement is governed by the laws of Nepal, including the National Civil Code, 2074.
16. GENERAL. This Agreement with its annexures is the entire agreement. Amendments are valid only in writing signed by both Parties. Notices shall be sent to the addresses stated above.
IN WITNESS WHEREOF the Parties have signed on the date first written above, in the presence of the witnesses below. Revenue stamp(s) as required have been affixed.
Owner (First Party): Signature: ____________ Name: ________________________ Date: ____________
Contractor (Second Party): Signature: ____________ Name: ________________________ Company seal (if any): ____________ Date: ____________
Witness 1: Signature: ____________ Name: ________________________ Citizenship No.: ____________ Address: ________________________
Witness 2: Signature: ____________ Name: ________________________ Citizenship No.: ____________ Address: ________________________
Annexures: Annex 1: Approved drawings (list attached). Annex 2: Bill of Quantities (BOQ). Annex 3: Material specifications and brands.
Attach: citizenship copies of both parties; contractor registration and PAN copies; Lal Purja copy; Naksa Pass copy.
Note: This is a general template for guidance. Get it reviewed by a lawyer before signing, especially for high value contracts.