Sydney’s harbour crossing project has passed two milestones at once, according to the New South Wales Government. The Western Harbour Tunnel team has finished excavating two huge underground reception chambers beneath Waverton, on the city’s North Shore, while the first of two giant tunnel boring machines approaches the halfway point of its drive beneath Sydney Harbour. The government confirmed completion of the chamber excavations on November 3, 2026, although it did not give the exact date the excavation work finished.
The chambers are the destination for the two machines, named Patyegarang and Barangaroo. Each chamber measures up to 23 metres high, 35 metres wide and 34 metres long, and each was dug out with specialised roadheaders rather than by the tunnel boring machines themselves. When the machines arrive, they will break through into these caverns and join up with a previously excavated 2.8 kilometre section running between Cammeray and Waverton. The two machines are currently boring the final 1.5 kilometre section of the tunnel beneath the harbour, at depths of up to 50 metres.
Western Harbour Tunnel: how the giant machines will be received
The reception plan is unusual, and it is one of the most interesting engineering details of the project. The machines are the largest tunnel boring machines ever used in the Southern Hemisphere, according to Tunnelling Journal, and they will not be lifted back to the surface when they finish. Instead, their cutterheads and shields will be detached, moved sideways inside the chambers and permanently sealed into the surrounding rock.
That approach avoids the difficult and costly job of recovering machines of this size from deep underground, but it demands chambers large enough, and strong enough, to take the machines apart safely in place. The chambers were therefore designed around dismantling, not just arrival, which explains their exceptional size.
The machines themselves are built for very hard, high pressure work. Each is a 15.7 metre diameter slurry machine made by CREG, weighing about 4,350 tonnes. They were assembled underground in purpose built launch chambers 44.7 metres beneath Birchgrove Oval. Patyegarang started digging in July 2026, followed by Barangaroo in August 2026. Each cutterhead carries 97 disc cutters, plus soft ground cutting tools and bucket scrapers, and is driven by 20 electric motors delivering almost 48,000 kilonewton metres of torque, while 60 hydraulic thrust cylinders provide more than 20,000 tonnes of thrust, according to Tunnelling Journal.
Most of the alignment runs through Hawkesbury Sandstone, but the machines must also cross a 180 metre mixed face section through a buried paleovalley made up of alluvial deposits and weathered sandstone. They are designed to work at pressures of up to 6 bar. As they advance, they will install about 13,000 precast concrete lining segments made at a dedicated facility at Emu Plains in western Sydney. Elsewhere on the project, roadheaders have excavated the northern tunnel sections between Waverton and Cammeray, with individual machines able to remove up to 1,000 tonnes of sandstone a day.
Why the harbour crossing matters
The completed Western Harbour Tunnel, a 6.5 kilometre route, will give Sydney its first new road harbour crossing in more than 35 years. It will connect the Warringah Freeway at North Sydney with the WestConnex network at the Rozelle Interchange, creating a second major road route across the harbour alongside the existing Sydney Harbour Tunnel and the Sydney Harbour Bridge.
That matters because harbour crossings are the pinch point for the whole city road network. Project projections reported by Build Australia put the expected traffic relief at 35 per cent on the Western Distributor, 20 per cent in the Sydney Harbour Tunnel and 17 per cent on the Sydney Harbour Bridge. New South Wales Minister for Roads Jenny Aitchison described the project as a once in a generation undertaking, saying the tunnel is taking shape deep beneath Sydney Harbour and that the two milestones show how much progress is being made.
Stage 2 of the project, which covers the harbour crossing, the associated underground civil works and the mechanical and electrical fit out of the finished tunnel, is being delivered by ACCIONA under a 4.24 billion Australian dollar contract awarded by Transport for New South Wales in December 2022, according to Tunnelling Journal.
What happens next on the project
Both machines are scheduled to break through into the Waverton chambers in 2027, completing the harbour drives and linking the new tunnels to the Cammeray to Waverton section. After breakthrough, the focus shifts to fitting out the tunnels, installing the road, ventilation, safety and control systems, and preparing the route for traffic. Opening to traffic remains scheduled for 2028, according to both sources.
The next year will therefore test the most delicate part of the plan: bringing two machines of record size into chambers carved out for the purpose, taking them apart underground, and sealing their largest parts into the rock, all while keeping the Western Harbour Tunnel programme on its 2028 timetable.
Sources: Tunnelling Journal, Giant TBM reception chambers completed beneath Sydney Harbour; Build Australia, Western Harbour Tunnel reaches milestone, November 3, 2026.