Hilsa-Simikot Road Blacktopping: 39 km Contract Signed, Humla to Get Its First Blacktopped Road

Infrastructure Development Minister Sunil Lamsal has announced that the Hilsa-Simikot road blacktopping project in Humla has moved into the construction phase, with a contract signed on Wednesday, November 18, 2026, to upgrade and blacktop 39 kilometres of the Karnali Corridor northern section. The minister said the agreement covers the Hilsa-Simikot road plan, which runs through some of the most remote settlements in Karnali Province.

What the Hilsa-Simikot road blacktopping contract covers

The contract covers two stretches of the road. The first runs from Kharpunath to Kharikhet, a distance of 18.2 kilometres, and the second runs from Kharikhet to Salisalla, a distance of 20.8 kilometres. Together, the two stretches add up to 39 kilometres of road to be upgraded and blacktopped. The work is estimated to cost nearly Rs 2 billion, and the contract sets a three-year schedule for completion.

The ministry had issued a notice of intent to accept the bids on Kartik 17, and the contract agreement was completed on Wednesday. The notice was published by the Karnali Corridor northern section office in Simikot, under the Department of Roads, and the contract signing follows that formal step. The work now moves from paperwork to construction on the ground.

Why the Hilsa-Simikot road blacktopping matters for Humla

The minister was direct about why this contract matters. “Humla has not received even one metre of blacktopped road from the central government so far,” Lamsal said, adding that the road and development dreams of Humla are dreams the ministry has taken as its own. Most settlements in Humla lie along the river corridors, and the minister said the upgrade and blacktopping of this road is expected to bring a fundamental change to the road network of the district.

The agreement follows the Karnali Corridor upgrade announced a day earlier, under which a multi-year programme worth more than Rs 3 billion was approved and contracts were signed for the 41 kilometre Khulalu-Salisalla section. Taken together, the two agreements show the ministry pushing the corridor forward in stages, from the southern sections toward Hilsa on the northern border. For Humla, a district that has waited years for a blacktopped road, the Hilsa-Simikot section is the stretch that reaches its district headquarters at Simikot and the border town of Hilsa.

What happens next

With the contract signed, construction work on the 39 kilometre stretch is set to proceed under the three-year schedule agreed with the contractor. The ministry will monitor progress against that timeline, and the completion of the blacktopping will give Humla its first blacktopped road from the central government. The next milestone to watch is the start of physical work on the Kharpunath to Kharikhet and Kharikhet to Salisalla stretches, and whether the pace holds through the winter working season in the high hills.

Related reading

Source: Minister Sunil Lamsal’s Facebook post, November 18, 2026.