Mude Charikot Road Construction Resumes After Years of Delay

The Mude Charikot road construction has picked up pace again after years of delay, with the remaining upgrade work on the Mude Charikot section of the Lamosangu Tamakoshi Jiri road finally moving forward. Infrastructure Development Minister Er. Sunil Lamsal announced on Monday, November 16, 2026, that the contractor resumed work just before Tihar, after the ministry began the process of terminating the contract.

Mude Charikot road construction: a history of delays

The project began under a contract signed in 2075 BS (2018-19), but it could not be completed even after repeated deadline extensions. In 2080 BS (2023), the government terminated the contract and decided to move the project forward through a new process. The construction company challenged that decision in court, which left the project in limbo for longer.

In 2081 BS (2024), the court ordered that the work be carried out by the original construction company. Even after four further deadline extensions, the remaining work did not move forward. The minister said the company was given one final chance to complete the work after the new government was formed, but the work still failed to gain pace during that period.

According to the minister, it was only after the ministry started the process of terminating the contract that the construction company resumed the remaining work, just before Tihar. The minister said the ministry is now monitoring the progress of the project on a daily basis.

Minister warns of fresh contract termination

Minister Lamsal warned that the daily monitoring will decide what happens next. He said, “We are monitoring the progress of the project daily. If work does not move forward at the designated pace, we are prepared to terminate the contract again and finish the remaining work.”

The warning puts the contractor under direct pressure to keep to the pace the ministry has set. If progress falls behind, the contract will be terminated again and the remaining work completed through another route.

Why the Mude Charikot section matters

The Mude Charikot section is part of the Lamosangu Tamakoshi Jiri road, a route that links communities across Dolakha district and connects Charikot, the district headquarters, toward Jiri. The road has been stranded for about four years, and the delay has left travellers and local residents waiting for a reliable connection through the area. Completing the upgrade would restore a dependable link for the district and for traffic heading toward Jiri.

For now, work is under way, and the coming weeks will show whether the resumed pace holds. The ministry’s daily checks mean any slowdown should be visible quickly, and the minister has made clear that the contractor will not be given another long extension.

Related reading

Source: Minister Sunil Lamsal’s Facebook post, November 16, 2026.