Madan Bhandari Highway Blacktopping Sindhuli Resumes After Disputes Settled

Madan Bhandari Highway blacktopping Sindhuli has resumed at Dhura Bazar, after construction on the highway section was stalled for a long time by local disputes. Infrastructure Development Minister Sunil Lamsal said on November 7, 2026 that blacktopping work has started at Dhura Bazar in Sindhuli, and that work is continuing even at night to make up for lost time.

The minister said construction had stopped at various places in Sindhuli and Makwanpur because of disputes over compensation. After the disputes were settled through facilitation, the stalled work has been restarted, he said. Compensation disputes have repeatedly slowed highway construction in the mid-hills, where land acquisition and payment for damaged crops and property often take longer than the construction schedule allows.

More Madan Bhandari Highway blacktopping Sindhuli sections to follow

Blacktopping will also begin within a month at Dhakalgaon and Khattar Bazar in Sindhuli, the minister said, with work planned to be completed within that period. In Makwanpur, construction is under way at Chaughada, while efforts are continuing to resolve the dispute in the Majhikhola area. The minister said he expects positive cooperation from local people as the work moves ahead.

The Madan Bhandari Highway, also known as the Pushpalal Highway, runs east to west through the mid-hill districts of Nepal and is one of the country’s national pride projects. It is meant to connect hill districts that have long depended on narrow and seasonal roads, giving farmers, traders and travellers a reliable all-weather route and an alternative to the East-West Highway in the Tarai. Sections of the highway have opened in stages, but several stretches have faced delays from difficult terrain, landslides, funding gaps and disputes over land and compensation.

For Sindhuli and Makwanpur, the resumption of blacktopping is significant because the highway passes through market towns and farming areas where a paved road changes daily life. A blacktopped road cuts travel time to district headquarters and to Kathmandu, lowers vehicle maintenance costs, and lets farm produce reach markets in better condition. Night work, which the minister said is continuing on the section, is a sign that the ministry wants the stalled stretches finished without another long delay.

Disputes over compensation remain the main risk. The minister said work in the Majhikhola area is still held up while a settlement is negotiated, and the pace of the remaining sections will depend on how quickly those local issues are resolved. The ministry’s approach in Sindhuli has been to settle disputes through facilitation with local people rather than to push construction ahead while objections stand, a course that takes time but avoids fresh blockages once work starts.

If the Dhakalgaon and Khattar Bazar sections are blacktopped within a month as announced, and the Majhikhola dispute is settled soon after, the Sindhuli and Makwanpur stretches of the highway will be closer to continuous blacktopped travel. The ministry has not given a date for full completion of the highway, which is being built in sections across many districts.

Related reading: the Saljhandi-Sandhikhark-Dhorpatan road progress (https://eve-construction.com/saljhandi-sandhikhark-dhorpatan-road-progress/) and the Kanchanpur Kamala highway upgrade (https://eve-construction.com/kanchanpur-kamala-highway-upgrade/).

Source: Minister Sunil Lamsal’s Facebook post, November 7, 2026 (https://www.facebook.com/ersunillamsal/posts/pfbid02XvDqwpMUiFwkS6DB1MEknKJacLgTEvyY778YnzkssXjN7Kteu8pTFnu95eC5GPczl).