Florida Everglades Reservoir Passes Halfway Mark on Underground Cutoff Wall

Wide reservoir embankment and calm water under a Florida sky, similar to the EAA Reservoir under construction in the Everglades
Photo: Pexels

The EAA Reservoir in southern Florida has passed the halfway mark on one of the most important structures nobody will ever see. According to the US Army Corps of Engineers, the foundation and cutoff wall for the reservoir are now 50 percent complete, with about eight miles of the 15.84 mile wall finished. The Corps announced the milestone in a press release on November 5, 2026, and said the work is running 34 days ahead of schedule.

What the EAA Reservoir cutoff wall does

A cutoff wall is a barrier buried in the ground beneath a dam. Water pushes against a dam, but it also looks for a way underneath, and the wall blocks that route. That matters more than usual here, because this reservoir sits on top of limestone, and limestone lets water through. The Corps knows the risk from experience. Wolf Creek Dam in Kentucky sits on limestone and spent decades leaking through the bedrock, and the fix was a second, deeper cutoff wall built while the lake was kept low.

The Florida wall is different in two useful ways. It goes in before the dam is built on top of it, so crews do not have to work around a finished structure, and it is a slurry wall made from slag cement, regular cement and bentonite clay. According to Forgen-Odin, the joint venture building it, the wall runs 35 to 60 feet deep. Crews dig a narrow trench held open by the wet mix, which then hardens in place, leaving a long, thin strip of stiff underground material sealing the ground beneath the future dam.

The machines moving a mountain of earth

Three draglines are working on the project right now, and one of them is unusual. According to North American Mining, which runs the draglines, its job is moving more than 25 million tons of earth for the 17.75 mile dam. The Corps counts 33.2 million cubic yards of excavation on the project in total.

The machine getting the attention is an Mteck 2100E, built by a Dutch crane maker. North American Mining lists it at 1,618,000 pounds, or 809 tons, with a 180 foot boom and a 20 to 22 cubic yard bucket. According to Mteck, its draglines run 18 to 22 hours a day, seven days a week in Florida. A fourth 2100E was reported to be on its way to the site in October 2026, joining one 2100E and two smaller 825E draglines already working there.

The scale of the finished reservoir is hard to picture. The Corps describes a 37 foot embankment holding water 23 feet deep across about 10,500 acres, with a design capacity of more than 78 billion gallons. It is closer to a giant above-ground pool than a lake in a valley, and the dam makes up for its modest height by running 17.75 miles.

Why the EAA Reservoir matters for the Everglades

The reservoir exists because Lake Okeechobee gets too full. When that happens, water is sent out toward both coasts, where the Corps says it does real damage to the estuaries, while the Everglades to the south does not get enough. The reservoir sits 27 miles south of the lake, and it is meant to catch that water and hold it until it can head south.

Before the water goes anywhere, it runs through a 6,500 acre treatment wetland next door. The Corps expects the whole setup to send as much as 470 billion gallons of clean water a year to the Everglades and Florida Bay. The South Florida Water Management District is handling the pump stations and the Blue Shanty Flow Way, which moves the water on toward the park and the bay.

What happens next

The foundation and cutoff wall are scheduled to finish in March 2028, according to the Corps. The dam contract, held by Thalle Construction and valued at 2.87 billion dollars, is due by December 2029. The Army and Florida struck a deal last year to finish the reservoir by 2029, when the original target was 2034. “Delivering it five years early is what happens when we build infrastructure, not paperwork,” said Lee Forsgren, the senior official performing the duties of the assistant secretary of the Army for civil works.

The second half of the wall has a little over a year to go, after the first half took close to four years, but much of that early time went to clearing land, digging out muck, blasting and preparing the foundation. The Corps says it has pulled the finish date in by 15 months. If the current pace holds, the wall will be done in early 2028, the dam will follow by the end of 2029, and the Everglades will start receiving the clean water the project was built to deliver.

Source: AutoNotion, The underground cutoff wall for a Florida reservoir built to hold more than 78 billion gallons is now 50 percent complete.