Maldhunga Bridge Geobags: Foundation Work Races Toward Completion
Maldhunga bridge geobags are the next step in the race to restore the flood-damaged crossing in Baglung, with the first
Maldhunga bridge geobags are the next step in the race to restore the flood-damaged crossing in Baglung, with the first
Malekhu Muglin road maintenance is being accelerated ahead of the festival season, with pothole filling, drain cleaning and opening, and
Tatopani border road repair is moving ahead at full speed, with retaining-wall construction and landslide clearing progressing rapidly on the
Nepal will need Rs 723.31 billion for recovery and reconstruction after the August 26 Bhotekoshi floods, according to the government’s
The Beni-Jomsom-Korala road drone fuel delivery operation has put reconstruction back on a fast track in Myagdi district, after floods
The Betrawati Bailey bridge installation is set to be completed within the next five days, bringing the restoration of the
The flood-damaged Beni-Jomsom road will be back in operation before Dashain, Infrastructure Development Minister Sunil Lamsal announced on October 5,
A road project in Kavrepalanchok that sat nearly idle for years has surged from 8 percent to more than 50
Nepal’s infrastructure ministry has announced a special price adjustment for the construction sector, a decision that directly answers contractors’ warnings
Nepal construction material prices are climbing across the board, according to the latest official data from the National Statistics Office.