Nepal Site Engineer Toolkit

Land units, material estimates, QC checks & rate analysis — per NBC, IS codes, DUDBC & DoR norms

Core Calculators

Steel Bar Weight

Formula: weight (kg/m) = D² / 162.2  ·  weight (kg/ft) = D² / 533, where D = diameter in mm

Concrete Materials Estimator

Dry volume factor 1.52 · cement 1440 kg/m³ · 1 bag = 50 kg

Brickwork Estimator

≈ 500 modular bricks per m³ of brickwork · mortar ≈ 0.25 m³ per m³

Unit Converter

Land & Local Units

Land Area Converter

Hilly: 1 ropani = 16 aana = 64 paisa = 256 daam · Terai: 1 bigha = 20 kattha = 400 dhur

Sut → mm Rebar Converter

Sut≈ mmStandard bar
3 sut9.510 mm
4 sut12.712 mm
5 sut15.916 mm
6 sut19.120 mm
8 sut25.425 mm
1 sut = 1/8 inch ≈ 3.175 mm — the size masons and site workers quote on site
Concrete & Masonry (DUDBC Norms)

Concrete Estimator — DUDBC

Dry volume = wet volume × 1.54 · 1 bag cement = 50 kg · Preset norms per DUDBC: M20 ≈ 8 bags/m³, M15 ≈ 6.3 bags/m³

Plaster & Screed Estimator

Dry mortar factor 1.33 · Preset norms: 12 mm ≈ 0.11 bags/m², 20 mm ≈ 0.18 bags/m² (1:4 mix, incl. wastage)
Quality Control (NBC / IS)

Concrete Cube Test Check

Strength = failure load (N) ÷ (150 × 150) mm² — standard 150 mm cube

Lap Length & Seismic Hooks (Fe 500)

Tension lap 40d–50d (50d typical on Nepal residential sites) · compression lap min 24d · 135° seismic hook = max(10d, 75 mm) per NBC 105:2020 / IS 13920

Stirrup Spacing & Ductile Detailing

LocationMax stirrup spacing (IS 13920)
Beam — within 2d of joint face (plastic hinge zone)min(d/4, 8 × smallest long. bar dia, 100 mm)
Beam — elsewhered/2
Column — within lo of joint facemin(smaller dimension/4, 6 × smallest long. bar dia, 100 mm)
Column confinement length lomax(larger dimension, clear height/6, 450 mm)
Stirrups need 135° seismic hooks, min max(10d, 75 mm) — see the Lap Length card · column lap splices only in the middle half of the clear height, never inside lo · NBC 105:2020 adopts equivalent ductile detailing for seismic design

Formwork Stripping Time

MemberStripping time
Walls, columns, vertical faces16 – 24 hours
Slab soffit (props left under)3 days
Beam soffit (props left under)7 days
Removal of props — slab ≤ 4.5 m span7 days
Removal of props — slab > 4.5 m span14 days
Removal of props — beam/arch ≤ 6 m span14 days
Removal of props — beam/arch > 6 m span21 days
Per IS 456 / NBC — props must remain until concrete gains adequate strength
Hill Works, Roads & Costing

Gabion Box Material

Standard: 100 × 120 mm double-twisted hexagonal mesh · mesh wire 10 SWG (3.0 mm), selvedge 8 SWG (4.0 mm), lacing 12 SWG (2.4 mm) · lacing wire ≈ 3–5% of mesh weight

Plum Concrete Estimator

60% mass concrete (M10/M15) + 40% plum boulders (150–300 mm) — for retaining walls & abutments on hill sites

Road Earthwork Volume

End-area: V = L/2 × (A₁ + A₂) · Prismoidal: V = L/6 × (A₁ + 4Am + A₂) — for cut/fill on hill roads

Pavement Material Sizing

DoR norms: GSB compaction factor 1.25–1.30 · WBM/WMM loose:compacted 1.30–1.35 · asphalt density 2.3–2.4 t/m³

Rate Analysis (DUDBC/DoR)

Unit rate = (material + labour + equipment) × 1.15 · contractor overhead & profit fixed at 15% · VAT 13% on the billable total · use District (Zilla) rates for the municipality
Quick Reference

Mortar Factors & Brickwork Norms

ItemNorm
Dry volume factor — concretewet volume × 1.54
Dry volume factor — mortar / plasterwet volume × 1.33 – 1.35
Standard brick (DUDBC)230 × 115 × 75 mm (9″ × 4.5″ × 3″)
9″ (full) brickwork530 – 560 bricks per m³ (≈ 15 per cft)
4.5″ (half) brickwork55 – 60 bricks per m²
1:6 cement-sand mortar, 9″ wall≈ 1.2 bags cement per m³ of brickwork
1 bag cement50 kg · 0.0347 m³
DUDBC norms — add 5% wastage on bricks and cement at ordering stage